Anglo-Continental - Case Study
Jul. 1, 2014
Courtesy ofModuleK Limited
Project: Dining Hall
Client: Anglo-Continental School of English
Completed: July 2014
Floor area: 180m²
Duration: 7 weeks
Value: £137k
Turnkey service elements completed:
- Design
- Groundworks
- Manufacture
- Delivery and installation
- Service connections
- Access footpaths
‘We are pleased with the final product, which was used successfully as a space in which our Young Learner students ate lunches and carried out activities in the summer.’
Modulek provided this busy language school with a large dining hall, capable of seating 144 diners, during spring and early summer of 2014 ready for the busy summer season.
Whilst excavating the groundworks an old swimming pool was uncovered. This required our structural engineer’s input to redesign the foundations. Despite this set back to the programme the building was completed in just 7 weeks.