ERG (Air Pollution Control) Ltd

CPL, Immingham - Case Study

SHARE
Nov. 5, 2025
  • Client: CPL
  • Site: Immingham
  • Application: 
    • Syngas treatment and integrated energy recovery for UK’s largest AD digestate gasification pilot plant
    • Syngas oxidation: CO, tars, hydrocarbons and solids
    • Waste heat used to dry feed material to plant
    • Gas inlet 198kg/h, 650oC

Most popular related searches

Equipment:

  • CS Direct Fired Thermal Oxidiser, ceramic fibre lining
  • CS Cyclone for dust removal
  • CS Mixing air mixing bustle
  • SS Fan and ductwork
  • SS Stack, 15m, double-skin

Year delivered: 2024