Scope of supply
- 1 pcs. Grit- Grease Scraper Unit with pinion rack drive system; Dry Parts = CS + Sand B. + Epoxy Coating, Wet Parts = CS + Galvanize.
- 4 pcs. Ø 40m. PST Scraper Bridges; Dry Parts = CS + Sand B. + Epoxy Coating, Wet Parts = CS + Galvanize.
- 3 pcs. Suction Type Longitudinal FST Scrapers with pinion rack drive system; Dry Parts = CS + Sand B. + Epoxy Coating, Wet Parts = CS + Galvanize.
- 1 pcs. Ø 65m. SST Suction Scraper Bridge; Dry Parts = CS + Sand B. + Epoxy Coating, Wet Parts = CS + Galvanize.
- 2 pcs. Ø 20m. Thickeners; Dry Parts = CS + Sand B. + Epoxy Coating, Wet Parts = CS + Galvanize.
- 4 pcs. 467 kW Pipe in Pipe Type Heat Exchangers, Completely from CS + Painting.