Lanco Babandh Power Ltd - Case Study

SHARE
Dec. 3, 2021
Courtesy ofLanco Group

Lanco Babandh Power is a coal fired thermal power project with two supercritical units of 660 MW each, located in Dhenkanal District, Orissa

Total Capacity : 2x660 MW (1320 MW)
Fuel Source : From Mahanadi Coalfields Ltd & Captive Coal Mine at Rampia
Water Source : From River Brahmani
Clearances : All Major clearances in place
EPC Contractor : Lanco Infratech Limited

Status
BTG (Boiler, Turbine & Generator):

  • Boiler Unit-1: Structure erection completed. Pressure parts erection to be started
  • Boiler Unit-2: 2 nos. ceiling girder erection in progress. Pressure parts erection to be started
  • ESP Unit-1: Collecting Electrode erection work in progress
  • ESP Unit-2: Structure Erection work in progress
  • PHB Unit -1: Deck Casting completed. EOT crane erection completed. Balance structure work in progress
  • PHB Unit - 2: Deck Casting in progress. Structure work in progress

BOP(Balance of Plant) :

  • DMPT: Vessels erection completed. Building structural works in progress
  • Chimney: shell construction up to 220 meters completed. Balance work in progress
  • Coal Handling Plant, Fuel Oil Handling system, Water System, Raw Water System: Civil construction works in progress

Electrical and C&I : Switch yard: 90% Tower foundations completed. Balance work in progress

Contact Address

Head Office : Lanco Babandh Power Limited
Lanco House, Plot No.397, Udyog Vihar,
Phase-III, Gurgaon - 122016
New Delhi Region, India
Phone +91 124 4741000
Fax +91 124 4741024
[email protected]

Plant Office : At/Po Kharagprasad
Dist : Dhenkanal, Odisha - 759121
Phone No. +91 6732 – 212180
[email protected]

Local Office : Plot No,- BDA/HIG 42, Gangadhar Meher Marg
Jayadev Vihar, Bhubneswar -751013
Phone : +91 674-2303688
Fax No : +91 674-2300566

Most popular related searches