ENTA Treatment Systems Engineering Contracting Corporation

Maritas Textile – Case Study

SHARE
Nov. 3, 2018

Project Name
Maritas Textile Wastewater Treatment Plant

Employer
Maritas Textile

Contractor
Enta Muhendislik Antma Taah. San. Ve Tic. Ltd. Sti.

Location of the plant
KAHRAMANMARAS/ TURKEY

Scope of work
Industrial Wastewater Treatment Plant

Contract Date
2012

Completion Date
2013

Flowrate of the plant: 2.200 m3/day:

Inlet Pollution Parameters:
COD: HOOmg/L:
BOD: 450 mg/LI
PH: 9-10
OIL & GREASE: 31 mg/ L
TEMPERATURE: 10-30°C:

Outlet Discharge Values:
COD: 350mg/L
PH: 6-9
OILS. GREASE: 10 mg/ L

Units of the Plant:

Physical Treatment

  • Static Screen

Chemical Treatment

  • Coagulation Basin
  • Flocculation Basin
  • Sedimentation Basin

Biological Treatment

  • Aeration Basin with Blower and Diffuser System
  • Sedimentation Basin

Sludge Dewatering

  • Sludge Thickening Tank
  • Filter Pres